The Great Belt Bridge will be lifted 84 times in a massive renovation.
DR-Inland in Denmark
Wednesday, November 04, 2026 • 2:30 PM UTC - in Denmark
Domestic ( https://www.dr.dk/nyheder/indland )
*******************************************************
The Great Belt Bridge to be lifted 84 times in major renovation
*******************************************************
The Great Belt Bridge has more than 25 years behind it and is worn in several places. That is why a major renovation will be getting underway over three years.
Two years ago, Sund & Bælt carried out a test lift. It was meant to demonstrate that it is possible to lift the bridge without affecting either traffic or the bridge's structure. (Photo: © Sund & Bælt, DR)
By
Casper Martin Henriques ( [email protected] ) 57 min. ago
Imagine having to lift something that is 110 metres long and weighs 5,500 tonnes.
That is what is going to happen on the Great Belt Bridge's West Bridge in the coming years.
There are 188 bridge bearings that need to be renovated. 44 of them must be replaced entirely.
- The bridge is approaching 30 years old, and the bearings ensure that the bridge can move without being damaged, says Finn Raun Gottfredsen, who is project chief at Sund & Bælt and responsible for the renovation project.
---------------
Bridge to be lifted
---------------
In order to get to the bridge bearings, the bridge sections must be lifted 20 millimetres so that the bearings can be removed. This will happen 84 times.
But even though it may sound like a major operation, it will not bother car traffic when the bridge sections are lifted, Finn Raun promises.
- Even though there are cars weighing one and a half tonnes and a lorry, they are small things in the grand scheme of things, he says.
It is a bit different on the bridge where the trains cross. There will be track closures with no trains on the bridge during the period when the bridge section is being lifted.
Finn Raun Gottfredsen estimates that the entire renovation will take around three years and is expected to cost 232 million kroner.
According to the plan, the renovation will begin in April 2027.